How to Repair Exposed Aggregate Concrete
Concrete pavement exponsed stones repairing process
1.concrete exposed aggregate pics:
2.Why suggest you use BC concrete repair material?
Fast early strength, 2h can restore traffic
High adhesion,compression,flexural strength
Abrasive resistance is 8-10 times of normal concrete
Waterproof,anti-freeze and hydrochloric acid corrosion resistance
Beautiful,small color difference with original road surface
3.Technical data:
Test items | Unit | Technical requirement | Test result | Individual conclusion | |
Setting time | Initial setting | Min | ≥15 | 25 | Meet requirement |
Final setting | ≤60 | 35 | |||
Compressive strength | 2h | Mpa | ≥20 | 32 | Meet requirement |
1d | ≥30 | 63 | |||
28d | ≥50 | 95 | |||
Pulling strength | 28d | Mpa | ≥1.0 | 2.8 | Meet requirement |
Expansion rate | 28d | / | 0.0%-0.1% | 0.02% | Meet requirement |
4.How to use?
1) Detailed process:
Identifying→Cleaning→Washing→Wetting→Cleaning→Adding water→Mixing→Paving→Curing
2) Tools & Materials:
Tools:
High pressure blower gun
high pressure water gun(or water sprayer with water pump)
Vertical mixer
Darby
Steel trowel
Water storage barrel
Plastic film
Materials:
BC type concrete repair material
Clean water
3) Repair steps:
Step 1: Select area need to be repaired.
Step 2: Clean out crushed stone, dust by high pressure blower gun.
Step 3: Wash repair area by high pressure water gun.
Step 4: Fully wetting repair surface, until it no longer seep water.
Step 5: Clean water out from repair surface by high pressure blower gun.
Step 6: Add 17-18% water.
Step 7: Stir evenly by vertical mixer, stirring time within 5 mins.
Step 8: Pour mixed repair material to repair surface, flatten by darby promptly.
Step 9: After final setting,purling and covering by geotextile to maintain immediately.
5.Package and Storage:
1)Package: Paper plastic composite bag packaging, 25Kg/bag.
2)Storage: Store in a cool, dry place, rainproof and moistureproof.
3)Storage period: 9 months